2011 - 2016 Capital Improvement Program

Project #9004, Elm Creek Interceptor  

Description:

Metropolitan Council has completed 12 miles of the main stem of the Elm Creek Interceptor. Eight of those miles extend from the CAB Interceptor in Brooklyn Park (Regent Ave) westerly to I-94 and CSAH 30 in Maple Grove (Phases I & II and Trench Sheeting). The other 4 miles are located between Elm Road in southern Maple Grove to Hamel in the City of Medina (Medina Leg). The City of Maple Grove has constructed 4.5 miles of the main stem linking these two Council interceptor segments, between I-94 southwesterly to Elm Road. Another 1-1/4 miles of a future branch to southeast Corcoran was constructed by Maple Grove. The Council will eventually acquire ownership of those sewers from the City.

Project Map

Click here to view the project's location map


In addition to the above completed projects, in 2005 relocation began of approximately 7,000 feet of the Elm Creek Interceptor along with 3,900 feet of the new Dayton-Hassan extension in coordination with MnDOT's work along CSAH 81. The relocation resulted from the MnDOT re-design of the realignment of CSAH 81 in Maple Grove for the future interchange with TH 610. This interceptor project was completed in 2007.

Phase 1 of the Dayton-Hassan Extension was completed in 2008. The remaining gravity sewer, renamed the North Rush Creek Extension, with service to northeast Corcoran, is under design. The timing of construction depends on the pace that development resumes in this sector. The shallow gravity sewer portion of the South Corcoran extension was completed in 2009. An associated lift station will be coordinated with Corcoran's trunk sewer improvements.


Purpose and Justification
:

The interceptor and its branches are needed to serve planned growth in the Elm Creek watershed, while maximizing the use of available capacity in the Council's interceptor system and Metropolitan Treatment Plant. Future growth beyond the capacity of the interceptor system is proposed to be handled by the Northwest Interceptor Improvements and in the long-term, the future proposed Crow River Water Reclamation Plant.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

Jan-90 Sep-02

$700,000

Approved

Design

Dec-94 Dec-12
$15,800,000

Approved

Construction

Mar-98 Dec-15

$58,500,000

Approved

Prior Authorization:

$75,000,000

2011 Budget Adjustment:

$0

Total 2011 Authorization:

$75,000,000

Future Authorizations:

$0

Total Project Cost:

$75,000,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2011
$65,440,000
$0
$65,440,000
2011 Budget
0
0
0
2012
1,000,000
0
1,000,000
2013
1,000,000
0
1,000,000
2014
3,000,000
0
3,000,000
2015
4,000,000
0
4,000,000
2016
0
0
0
2017 - 2021
0
0
0
2022 - 2026
0
0
0
Contingency
560,000
0
560,000
Totals
$75,000,000
$0
$75,000,000

return to top

Impact on O&M Costs:

Gravity system will increase O & M costs very little.

return to top

 

 

© 2012 Metropolitan Council. All Rights Reserved. · 390 Robert St. N., St. Paul, MN 55101 · Phone: 651-602-1000 · TTY: 651-291-0904