2008 - 2017 Capital Improvement Program

Project #9004, Elm Creek Interceptor  

Description:

Metropolitan Council has completed 12 miles of the main stem of the Elm Creek Interceptor. Eight   of those miles extend from the CAB Interceptor in Brooklyn Park (Regent Ave) westerly to I-94   and CSAH 30 in Maple Grove (Phases I & II and Trench Sheeting). The other 4 miles are located   between Elm Road in southern Maple Grove to Hamel in the City of Medina (Medina Leg). The City   of Maple Grove has constructed 4.5 miles of the main stem linking these two Council interceptor   segments, between I-94 southwesterly to Elm Road. Another 1-1/4 miles of a future branch to   southeast Corcoran was constructed by Maple Grove. The Council will eventually acquire  ownership  of those sewers from the City.

Project Map

Click here to view the project's location map


In addition to the above completed projects, in 2005 relocation began of approximately 7,000 feet of the Elm Creek Interceptor along with 3,900 feet of the new Dayton-Hassan extension in coordination with MnDOT's work along CSAH 81. The relocation resulted from the MnDOT re-design of the realignment of CSAH 81 in Maple Grove for the future interchange with TH 610. This interceptor project was completed in 2007.

A facility planning update for future branches of the Elm Creek Interceptor and alternatives for wastewater service to northwest Hennepin County was completed in 2002. The recommendations of this study call for gravity branches of the Elm Creek Interceptor to be extended to southwest Dayton and northeast Corcoran and a separate branch to southeast Corcoran. As flows from the Elm Creek Interceptor increase, the receiving CAB Interceptor will need a gravity diversion interceptor tunneled from Brooklyn Park, under the Mississippi River, to an existing interceptor in Fridley. The developing areas of the City of Rogers and Hassan Township are proposed to be handled by a Council-owned wastewater treatment plant in that area. Northern Dayton is planned to be served by a branch to be extended from the CAB Interceptor in Champlin, which is designated as the Dayton-Champlin Interceptor.

The design of the South Corcoran and Dayton-Hassan extensions began in 2003. Construction of the South Corcoran Extension, and Dayton-Hassan Extension began in 2006 and be completed in 2008. The remainder of the Dayton-Hassan extension, with service to northeast Corcoran and southern Hassan Township, is scheduled for completion in 2009.


Purpose and Justification
:

The interceptor and its branches are needed to serve planned growth in the Elm Creek watershed, while maximizing the use of available capacity in the Council's interceptor system and Metropolitan Treatment Plant. Future growth beyond the capacity of the interceptor system is proposed to be handled by the Northwest Interceptor Improvements and in the long-term, the future proposed Crow River WWTP.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

Jan-90 Sep-02

$700,000

Approved

Design

Dec-94 Dec-05
$15,800,000

Approved

Construction

Mar-98 Dec-09

$55,500,000

Approved

Prior Authorization:

$72,000,000

2008 Budget Adjustment:

$0

Total 2008 Authorization:

$72,000,000

Future Authorizations:

$0

Total Project Cost:

$72,000,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2008
$59,782,000
$0
$59,782,000
2008 Budget
5,000,000
0
5,000,000
2009
4,300,000
0
4,300,000
2010
0
0
0
2011
0
0
0
2012
0
0
0
2013
0
0
0
2014
0
0
0
2015
0
0
0
2016
0
0
0
2017
0
0
0
Post-2017
0
0
0
Contingency
2,918,000
0
2,918,000
Totals
$72,000,000
$0
$72,000,000

return to top

Impact on O&M Costs:

Gravity system will increase O & M costs very little.

return to top

 

 

© 2009 Metropolitan Council. All Rights Reserved. · 390 Robert St. N., St. Paul, MN 55101 · Phone: 651-602-1000 · TTY: 651-291-0904