2011 - 2016 Capital Improvement Program

Project #8065, Interceptor WO-500 Rehabilitation  

Description:

This project provides for the rehabilitation of approximately 12,000 lineal feet of interceptor with Cured-in-place-Pipe (CIPP).

 

Project Map

Click here to view the project's location map

Purpose and Justification:

The video inspection of Interceptor 1-WO-500 in Woodbury revealed significant hydrogen sulfide damage to the Reinforced Concrete Pipe (RCP). Steel reinforcement is visible and/or missing in several locations. Several locations also have significant I/I entering the Council’s interceptor.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

N/A N/A

$0

Approved

Design

Jan-07 Dec-10

$100,000

Approved

Construction

Jan-11 Dec-15

$7,700,000

Approved

Prior Authorization:

$2,200,000

2011 Budget Adjustment:

$5,600,000

Total 2011 Authorization:

$7,800,000

Future Authorizations:

$0

Total Project Cost:

$7,800,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2011
$114,000
$0
$114,000
2011 Budget
2,000,000
0
2,000,000
2012
2,000,000
0
2,000,000
2013
1,000,000
0
1,000,000
2014
1,000,000
0
1,000,000
2015
1,000,000
0
1,000,000
2016
0
0
0
2017 - 2021
0
0
0
2022 - 2026
0
0
0
Contingency
686,000
0
686,000
Totals
$7,800,000
$0
$7,800,000

return to top

Impact on O&M Costs:

The impact will generally be minor due to the rehabilitation nature of the project.

return to top

 

 

© 2012 Metropolitan Council. All Rights Reserved. · 390 Robert St. N., St. Paul, MN 55101 · Phone: 651-602-1000 · TTY: 651-291-0904