2008 - 2017 Capital Improvement Program

Project #8065, Interceptor WO-500 Rehabilitation  

Description:

This project provides for the repair of a total of 8,483 lineal feet of interceptor with Cured-in-place-Pipe (CIPP).

 

Project Map

Click here to view the project's location map

Purpose and Justification:

The video inspection of Interceptor 1-WO-500 in Woodbury revealed significant hydrogen sulfide damage to the Reinforced Concrete Pipe (RCP). Steel reinforcement is visible and/or missing in several locations. Several locations also have significant I/I entering the Council’s interceptor.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

N/A N/A

$0

Approved

Design

Jan-07 Feb-07

$100,000

Approved

Construction

Mar-07 Aug-08

$2,100,000

Approved

Prior Authorization:

$0

2008 Budget Adjustment:

$2,200,000

Total 2008 Authorization:

$2,200,000

Future Authorizations:

$0

Total Project Cost:

$2,200,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2008
$1,000,000
$0
$1,000,000
2008 Budget
1,000,000
0
1,000,000
2009
0
0
0
2010
0
0
0
2011
0
0
0
2012
0
0
0
2013
0
0
0
2014
0
0
0
2015
0
0
0
2016
0
0
0
2017
0
0
0
Post-2017
0
0
0
Contingency
200,000
0
200,000
Totals
$2,200,000
$0
$2,200,000

return to top

Impact on O&M Costs:

The impact will generally be minor due to the rehabilitation nature of the project.