2008 - 2017 Capital Improvement Program

Project #8062, Metro Solids - Biosolids Storage  

Description:

This project will implement bio-solids stabilization, storage and utilization, to supplement the fluid   bed incineration and energy recovery system that has recently been completed. This project is   part of the MWWTP Solids Processing Facility Plan.

Project Map

Click here to view the project's location map

Purpose and Justification:

Alkaline stabilization facilities were incorporated into the Solids Management Building, however storage facilities were deferred pending further development of a bio-solids management plant. This project will include a review of USEPA Class A regulations to take advantage of any technology improvements since the original Facility Plan. Major changes to the existing alkaline stabilization process are not anticipated. Biosolids haulers and other end-users will be contacted to help develop a flexible plan that leverages off-site storage options.

The project will also evaluate the viability of providing new anaerobic digesters to process up to 50 dry tons per day (DTPD). Digestion would be available during scheduled incinerator maintenance or to provide transitional capacity to avoid running a third incinerator. Alkaline stabilization would continue to be retained as a back-up process. Recovery and utilization of digester gas would be included in the economic analysis of this alternative. Digestion would also require modifications for storage, dewatering and load-out of digested bio-solids.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

Jul-06 Jun -07

$500,000

Approved

Design

Jul-07 Dec-08

$1,000,000

Approved

Construction

Jan-09 Jun-11

$10,500,000

Approved

Prior Authorization:

$12,000,000

2008 Budget Adjustment:

$0

Total 2008 Authorization:

$12,000,000

Future Authorizations:

$0

Total Project Cost:

$12,000,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2008
$100,000
$0
$100,000
2008 Budget
 400,000
0
400,000
2009
1,000,000
0
1,000,000
2010
5,000,000
0
5,000,000
2011
5,000,000
0
5,000,000
2012
0
0
0
2013
0
0
0
2014
0
0
0
2015
0
0
0
2016
0
0
0
2017
0
0
0
Post-2017
0
0
0
Contingency
500,000
0
500,000
Totals
$12,000,000
$0
$12,000,000

return to top

Impact on O&M Costs:

The actual impact on O&M costs is dependent upon the alternative chosen.

return to top

 

 