2008 - 2017 Capital Improvement Program

Project #8057, Golden Valley Area Improvements  

Description:

This project consists of capacity relief and rehabilitation of the Plymouth-New Hope-Golden Valley  Interceptor system.

Project Map

Click here to view the project's location map

Purpose and Justification:

The Interceptor Master Plan identified several needs in this service area, including rehabilitation and increased capacity for the Plymouth Lift station L29, rehabilitation and increased capacity for New Hope Lift Station L41 and its forcemain, and rehabilitation and increased capacity for gravity sewers in Golden Valley.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

Jan-06 Dec-07
$300,000
Approved

Design

Jan-08 Feb-09
$2,700,000
Approved

Construction

Mar-09 Dec-12

$27,000,000

Future

Prior Authorization:

$3,000,000

2008 Budget Adjustment:

$0

Total 2008 Authorization:

$3,000,000

Future Authorizations:

$27,000,000

Total Project Cost:

$30,000,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2008
$400,000
$0
$400,000
2008 Budget
  1,500,000
0
1,500,000
2009
1,000,000
6,000,000
7,000,000
2010
0
7,000,000
7,000,000
2011
0
7,000,000
7,000,000
2012
0
7,000,000
7,000,000
2013
0
0
0
2014
0
0
0
2015
0
0
0
2016
0
0
0
2017
0
0
0
Post-2017
0
0
0
Contingency
100,000
0
100,000
Totals
$3,000,000
$27,000,000
$30,000,000

return to top

Impact on O&M Costs:

This project will have minimal impact on O&M costs.