2008 - 2017 Capital Improvement Program

Project #8055, Lift Station Rehabilitation  

Description:

This project consists of improvements to Lift Stations L-3, L-6, L-7, L-10, L-13, L-30, L-35, and L-  56 and L-66. The project will replace obsolete, aging equipment and increase the lift stations   pumping capacity. The L-7 forcemain will also be replaced under this project.

Project Map

Click here to view the project's location map

Purpose and Justification:

The Interceptor System Master Plan (2002) recommended lift station improvements. This project will renovate these aging lift stations, which are 30 to 40 years old and will increase capacity as needed. The other, older lift stations in the system are generally part of a larger interceptor system project, i.e. Blue Lake, Northeast, or Northwest.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

Jan-06 Sep-06
$1,030,000
Approved

Design

Oct-06 Dec-07
$2,220,000
Approved

Construction

Jan-08 Dec-12

$32,750,000

Approved

Prior Authorization:

$5,000,000

2008 Budget Adjustment:

$2,500,000

Total 2008 Authorization:

$7,500,000

Future Authorizations:

$28,500,000

Total Project Cost:

$36,000,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2008
$501,000
$0
$501,000
2008 Budget
  4,000,000
0
4,000,000
2009
2,500,000
5,500,000
8,000,000
2010
0
9,000,000
9,000,000
2011
0
8,000,000
8,000,000
2012
0
6,000,000
6,000,000
2013
0
0
0
2014
0
0
0
2015
0
0
0
2016
0
0
0
2017
0
0
0
Post-2017
0
0
0
Contingency
499,000
0
499,000
Totals
$7,500,000
$28,500,000
$36,000,000

return to top

Impact on O&M Costs:

Impact generally minor as the projects are of a rehabilitative nature.

return to top

 

Lift Station Projects

Project #805510

Facility
Location
Scope
L-3
Hugo
Work at this lift station will include installation of two 75 hp pumps, suction valves at two locations, and necessary header piping.
L-6
White Bear Lake
A new three-pump submersible pumping station will replace the existing factory build station installed in 1961. 
L-10
Little Canada
Anew submersible pumping station will be installed at the present site to replace a factory built pumping station installed in the 1970’s. Upon completion, this facility will be re-conveyed to the City of Little Canada and is being designed and constructed to meet City requirements regarding its configuration, pumps and control system. 
L-56
Eagan
A new two-pump submersible pumping station will replace a factory- built station constructed in the 1960’s. This facility will be re-conveyed to the City of Eagan and is being designed and constructed to meet City requirements regarding its configuration, pumps and control system. 

Project #805520

Facility
Location
Scope
L-7
Mahtomedi
The work will include installation of three new dry-pit  pumps and motors and the necessary pipe header modifications to allow use of either or both forcemain barrels. A new supervisory control and MCC system will be provided and the HVAC system will be replaced
L-30
Crystal
This station, originally constructed in 1955, will receive a complete overhaul. New pumps, valves, and piping will be provided. Supervisory controls and the MCC will be replaced. 
L-35
Mounds View
This pumping station, originally constructed in 1966, will receive a complete overhaul. New pumps, valves, and piping will be provided. Supervisory controls and the MCC will be replaced. 

 

Project #805530

Facility
Location
Scope
L-7 FM
Mahtomedi
The present forcemain will be replaced and abandoned. The forcemain will be realigned along Lincolntown Road and Long Lake Road and discharge into interceptor MSB 7121. The forcemain will be approximately 10,000 lf long and will consist of twin 16-inch diameter forcemain barrels with cross-over structures. (Location Map)

 

Project #805540

Facility
Location
Scope
L-13
Burnsville

The pumping station is in need of a total rehabilitation. New pumps, valves, and piping will be provided. Supervisory controls and the MCC will be replaced. and the lighting, plumbing and mechanical systems will be replaced. Rehabilitation of the wet well was completed in 2007.

A parallel forcemain barrel will be installed to the present discharge location. The option to discharge into a siphon barrel will be maintained.  The existing forcemain will be rehabilitated to remedy the reaches where breaks have occurred.

L-66
Savage
The present facility was constructed in 1988.  The pumping station and dual barrel forcemain are in good condition. Capacity improvements are required to boost the station capacity and meet the projected service requirements. A fourth pump will be installed in the existing station. In addition the project includes modifications to the pipe manifold, and control system. The wet well will be cleaned and coated with a corrosion resistant coating. The completed improvements will deliver the needed capacity utilizing both forcemain barrels.

 

 

© 2008 Metropolitan Council. All Rights Reserved. · 390 Robert St. N., St. Paul, MN 55101 · Phone: 651-602-1000 · TTY: 651-291-0904