> Water > Capital Improvement Program
| Project
#8055, Lift Station Rehabilitation |
|
Description:
This project consists of improvements to Lift Stations L-3, L-6, L-7, L-10, L-13, L-30, L-35, and L-56 and L-66. The project will replace obsolete, aging equipment and increase the lift stations' pumping capacity. The L-7 forcemain will also be replaced under this project.
|
Project Map

|
Purpose
and Justification:
The Interceptor System Master Plan (2002) recommended lift station improvements. This project will renovate these aging lift stations, which are 30 to 40 years old and will increase capacity as needed. The other, older lift stations in the system are generally part of a larger interceptor system project, i.e. Blue Lake, Northeast, or Northwest.
return
to top
Project
Authorization:
|
Project
Schedule |
Authorizations |
|
Start |
End |
Funding |
Status |
Prelim.
Engr. |
Jan-06 |
Mar-10 |
$1,030,000 |
Approved |
Design |
Oct-06 |
Oct-11 |
$2,220,000 |
Approved |
Construction |
Mar-09 |
Dec-15 |
$32,750,000 |
Approved |
Prior Authorization: |
$36,000,000 |
|
2011 Budget
Adjustment: |
$0 |
|
Total 2011
Authorization: |
$36,000,000 |
|
Future
Authorizations: |
$0 |
|
Total Project
Cost: |
$36,000,000 |
|
return
to top
Projected
Cash Flow:
|
Authorized |
Future |
Total |
Prior to 2011 |
$3,968,000 |
$0 |
$3,968,000
|
2011 Budget |
500,000 |
0 |
500,000 |
2012 |
2,500,000 |
0 |
2,500,000 |
2013 |
10,000,000 |
0 |
10,000,000 |
2014 |
10,000,000 |
0 |
10,000,000 |
2015 |
9,000,000 |
0 |
9,000,000 |
2016 |
0 |
0 |
0 |
2017 - 2021 |
0 |
0 |
0 |
2022 - 2026 |
0 |
0 |
0 |
Contingency |
32,000 |
0 |
32,000 |
Totals |
$36,000,000 |
$0 |
$36,000,000 |
return
to top
Impact
on O&M Costs:
Impact generally minor as the projects are of a rehabilitative nature.
return
to top
Lift Station Projects |
Project #805510
Facility |
Location |
Scope |
L-3 |
Hugo |
Work at this lift station will include installation of two 75 hp pumps, suction valves at two locations, and necessary header piping. |
L-6 |
White Bear Lake |
A new three-pump submersible pumping station will replace the existing factory build station installed in 1961. |
L-10 |
Little Canada |
A new submersible pumping station will be installed at the present site to replace a factory built pumping station installed in the 1970’s. Upon completion, this facility will be re-conveyed to the City of Little Canada and is being designed and constructed to meet City requirements regarding its configuration, pumps and control system. |
L-56 |
Eagan |
A new two-pump submersible pumping station will replace a factory- built station constructed in the 1960’s. This facility will be re-conveyed to the City of Eagan and is being designed and constructed to meet City requirements regarding its configuration, pumps and control system. |
|
Project #805520
Facility |
Location |
Scope |
L-7 |
Mahtomedi |
The work will include installation of three new dry-pit pumps and motors and the necessary pipe header modifications to allow use of either or both forcemain barrels. A new supervisory control and MCC system will be provided and the HVAC system will be replaced |
|
Project #805530
Facility |
Location |
Scope |
L-7 FM |
Mahtomedi |
The present forcemain will be replaced and abandoned. The forcemain will be realigned along Lincolntown Road and Long Lake Road and discharge into interceptor MSB 7121. The forcemain will be approximately 10,000 lf long and will consist of twin 16-inch diameter forcemain barrels with cross-over structures.(Location Map) |
|
Project #805540
Facility |
Location |
Scope |
L-30 |
Crystal |
This station, originally constructed in 1955, will receive a complete overhaul. New pumps, valves, and piping will be provided. Supervisory controls and the MCC will be replaced. |
L-35 |
Mounds View |
This pumping station, originally constructed in 1966, will receive a complete overhaul. New pumps, valves, and piping will be provided. Supervisory controls and the MCC will be replaced. |
L-66 |
Savage |
The present facility was constructed in 1988. The pumping station and dual barrel forcemain are in good condition. Capacity improvements are required to boost the station capacity and meet the projected service requirements. A fourth pump will be installed in the existing station. In addition the project includes modifications to the pipe manifold, and control system. The wet well will be cleaned and coated with a corrosion resistant coating. The completed improvements will deliver the needed capacity utilizing both forcemain barrels. |
Project #805550
Facility |
Location |
Scope |
L-13 |
Burnsville |
The pumping station is in need of a total rehabilitation. New pumps, valves, and piping will be provided. Supervisory controls and the MCC will be replaced. and the lighting, plumbing and mechanical systems will be replaced. Rehabilitation of the wet well was completed in 2007.
A parallel forcemain barrel will be installed to the present discharge location. The option to discharge into a siphon barrel will be maintained. The existing forcemain will be rehabilitated to remedy the reaches where breaks have occurred. |
|