| Project #8040, Burnsville Interceptor Rehabilitation | |
Description: This project provides for the rehabilitation of approximately 17,500 feet of Interceptor 3-BV-35. Rehabilitation is required due to hydrogen sulfide corrosion, exposed reinforcement, inflow/infiltration, offset joints, separated joints, extensive root damage and cracks. |
Inspection has revealed that the interceptor is in need of repair due to extensive root damage, cracks, corrosion damage and excessive inflow/infiltration. The inspection reports indicate moderate risk of failure, but severe impact if it fails.
Project Schedule |
Authorizations |
|||
Start |
End |
Funding |
Status |
|
Prelim. Engr. |
Jan-03 | Dec-04 | (Under Interceptor Rehab. Program) |
|
Design |
Jan-05 | Jun-07 | $50,000 |
Approved |
Construction |
Jul-07 | Dec-08 | $2,450,000 |
Approved |
Prior Authorization: |
$2,500,000 |
|||
2008 Budget Adjustment: |
$0 |
|||
Total 2008 Authorization: |
$2,500,000 |
|||
Future Authorizations: |
$0 |
|||
Total Project Cost: |
$2,500,000 |
|||
Authorized |
Future |
Total |
|
Prior to 2008 |
$422,000 |
$0 |
$422,000 |
2008 Budget |
2,000,000 |
0 |
2,000,000 |
2009 |
0 |
0 |
0 |
2010 |
0 |
0 |
0 |
2011 |
0 |
0 |
0 |
2012 |
0 |
0 |
0 |
2013 |
0 |
0 |
0 |
2014 |
0 |
0 |
0 |
2015 |
0 |
0 |
0 |
2016 |
0 |
0 |
0 |
2017 |
0 |
0 |
0 |
Post-2017 |
0 |
0 |
0 |
Contingency |
78,000 |
0 |
78,000 |
Totals |
$2,500,000 |
$0 |
$2,500,000 |
Impact generally minor due to the rehabilitation nature of the project.