2008 - 2017 Capital Improvement Program

Project #8039, Chaska Lift Station  

Description:

The project consists of the design and construction of a new 21 mgd custom built replacement  pumping station at the former WWTP site to provide long-term capacity to serve Chaska, Carver,   and areas to the west. The project includes the demolition of wastewater treatment facilities from   the phased-out Chaska WWTP.

Project Map

Click here to view the project's location map

Purpose and Justification:

The projected development within the Cities of Chaska and Carver will cause wastewater flow to exceed the present interim lift station capacity by the year 2009.

return to top

 

Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

Jan-04 Mar-04

$21,000

Approved

Design

Apr-04 Dec-06

$679,000

Approved

Construction

Jan-07 Dec-09

$12,300,000

Approved

Prior Authorization:

$13,000,000

2008 Budget Adjustment:

$0

Total 2008 Authorization:

$13,000,000

Future Authorizations:

$0

Total Project Cost:

$13,000,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2008
$3,979,000
$0
$3,979,000
2008 Budget
  6,000,000
0
6,000,000
2009
3,000,000
0
3,000,000
2010
0
0
0
2011
0
0
0
2012
0
0
0
2013
0
0
0
2014
0
0
0
2015
0
0
0
2016
0
0
0
2017
0
0
0
Post-2017
0
0
0
Contingency
21,000
0
21,000
Totals
$13,000,000
$0
$13,000,000

return to top

Impact on O&M Costs:

The annual O/M effort will increase as the project adds larger facilities to operate and maintain.