2008 - 2017 Capital Improvement Program

 

Project #8027, South St Paul LS/FM Improvements  

Description:

The project updated the existing lift station. Converted from a former Wastewater Treatment   Plant   (WWTP) in 1986, the lift station still was utilizing some of the old equipment from the   WWTP.  Completed in 2006, the project included the replacement of the screen handling facilities;   electrical  equipment; pumps and motors; odor control; standby power; and improvement to wet    well access and to the secondary building. The project also includes the replacement of the    existing  48-inch-diameter forcemain with a dual forcemain for reliability of conveyance to the    Metropolitan WWTP. This forcemain portion of the project includes river crossing and conveyance    through the Metropolitan WWTP to the plant headworks.

Project Map

Click here to view the project's location map


Purpose and Justification
:

The South St Paul lift station L-65 was converted from a former Wastewater Treatment Plant (WWTP) in 1986. The lift station has undergone a few renovations since that time. However, some of the old parts from the WWTP were still in use at the lift station. Most of the lift station components were 30 years old and were in poor condition. The bar screens were old and in very poor condition having been patched and rebuilt numerous times. The electrical panels were mainly from the WWTP and because of their age many of the parts were no longer made, causing problems for maintenance. The back-up power supply, both the primary and secondary were in need of major renovation and had a history of failure. The access to the wet was in a compromising location that was difficult to enter, creating a safety concern and nuisance for workers. Also, the site was a source of occasional odor complaints.

Construction activities associated with the Wakota Bridge project revealed that the existing 48" forcemain was more severely deteriorated then previous inspections had revealed. The forcemain is composed of prestressed concrete cylinder pipe with the Interpace Class IV wire that is prone to hydrogen embrittlement. Pipe exposed as part of MNDOT's Wakota Bridge project exhibited cracks in the protective cement mortar coating, delaminated protective cement mortar coating, and corroded and broken prestressed wires. This compromises the integrity of the forcemain. The 48-inch-diameter pipe will be replaced with a more appropriately sized 36-inch pipe. A second 36-inch pipe also will be installed for reliability.

return to top


Project Authorization:

Project Schedule

Authorizations

Start

End

Funding

Status

Prelim. Engr.

Jan-03
Feb-05

$900,000

Approved

Design

May-03
Jul-06
$2,300,000

Approved

Construction

Apr-04
Dec-10

$41,800,000

Approved

Prior Authorization:

$45,000,000

2008 Budget Adjustment:

$0

Total 2008 Authorization:

$45,000,000

Future Authorizations:

$0

Total Project Cost:

$45,000,000

return to top

   Projected Cash Flow:

Authorized

Future

Total

Prior to 2008
$8,908,000
$0
$8,908,000
2008 Budget
 15,000,000
0
15,000,000
2009
15,000,000
0
15,000,000
2010
6,000,000
0
6,000,000
2011
0
0
0
2012
0
0
0
2013
0
0
0
2014
0
0
0
2015
0
0
0
2016
0
0
0
2017
0
0
0
Post-2017
0
0
0
Contingency
92,000
0
92,000
Totals
$45,000,000
$0
$45,000,000

return to top

Impact on O&M Costs:

Expect that the overall yearly O/M effort will remain the same. The pumps, electrical, instrumentation and controls should require less maintenance. However, there will be some additional effort for maintaining a standby generator and the biofilter.

return to top

 

 

© 2009 Metropolitan Council. All Rights Reserved. · 390 Robert St. N., St. Paul, MN 55101 · Phone: 651-602-1000 · TTY: 651-291-0904