| Project
#8003, Mpls/St Paul Interceptor Improvements |
|
Description: This project provides for the rehabilitation of the core wastewater conveyance facilities in Minneapolis and St. Paul. Ranging in size from 54” to 13’ – 10” in diameter, some of these sewers have been in service for 60 or more years. This core interceptor system conveys more than 200 MGD to the Metropolitan Treatment Plant. It is characterized by large size, high flows and difficult access. Access shafts are as deep as 193 feet, and a few are located in underground caves and in ravines. The facility planning will include a review of the inspection findings, and will recommend alternative means to improve and repair the core interceptor system. A major project is relocation of the Oak Street Interceptor to accommodate the new Gophers Stadium. The project will also result in separating the existing sanitary sewer from being located inside the storm sewer. |
The project will correct problems with the aged, existing interceptors to assure system integrity and function and to avoid potential very costly emergency repairs to correct failures when they occur. The Oak Street Sewer Replacement project provides the opportunity to construct the sewer segments in conjunction with the new Gopher Stadium work at a lower cost and with less disruption.
Project Schedule |
Authorizations |
|||
Start |
End |
Funding |
Status |
|
Prelim. Engr. |
Jan-00 | Dec-07 | $2,000,000 |
Approved |
Design |
Jan-05 | Dec-09 | $4,000,000 |
Approved |
Construction |
Mar-06 | Dec-18 | $34,000,000 |
Approved |
Prior Authorization: |
$30,000,000 |
|||
2009 Budget Adjustment: |
$0 |
|||
Total 2009 Authorization: |
$30,000,000 |
|||
Future Authorizations: |
$10,000,000 |
|||
Total Project Cost: |
$40,000,000 |
|||
Authorized |
Future |
Total |
|
Prior to 2009 |
$8,800,000 |
$0 |
$8,800,000 |
2009 Budget |
7,000,000 |
0 |
7,000,000 |
2010 |
3,000,000 |
0 |
3,000,000 |
2011 |
0 |
0 |
0 |
2012 |
0 |
0 |
0 |
2013 |
0 |
0 |
0 |
2014 |
0 |
0 |
0 |
2015 |
0 |
0 |
0 |
2016 |
0 |
0 |
0 |
2017 |
0 |
0 |
0 |
2018 |
10,000,000 |
0 |
10,000,000 |
Post-2018 |
1,000,000 |
10,000,000 |
11,000,000 |
Contingency |
200,000 |
0 |
200,000 |
Totals |
$30,000,000 |
$10,000,000 |
$40,000,000 |
The project will significantly reduce emergency repair costs over potential costs without the project.
Current Projects
|
© 2009 Metropolitan Council. All Rights Reserved. · 390 Robert St. N., St. Paul, MN 55101 · Phone: 651-602-1000 · TTY: 651-291-0904