| Map ID | Project Name and Description | Phase Authorized in 2011 |
|---|---|---|
| (Click on the project name for additional project details) | ||
| 1 |
MWWTP Nutrient Removal - This project will evaluate the potential improvement requirements for various regulatory scenarios for phosphorus, nitrogen, and other wastewater constituents. |
Prelim. Engr. |
| 2 | MWWTP Rehabilitation and Facilities Improvements - Consists of the following: (1) on-site central standby power facility using diesel generators; (2) rehabilitation of in-plant power distribution system, process control system, and plant water systems; (3) rehabilitation of sludge storage tanks and several other structural components of the plant; (4) process enhancements for the fluidized bed incineration system; (5) replacement of sludge collection equipment and other process equipment; and (6) decommissioning or re-use of buildings that are no longer used for their original process functions.. |
Construction |
| 3 |
MWWTP Solids - Biosolids Storage - This project will implement bio-solids stabilization, storage and utilization, to supplement (capacity and reliability) the fluid bed incineration and energy recovery system that began operation in 2005. This project is part of the MWWTP Solids Processing Facility Plan. |
Construction |
| Map ID | Project Name and Description | Phase Authorized in 2010 |
|---|---|---|
| (Click on the project name for additional project details) | ||
| 4 | Empire Plant - Solids Processing - Provides additional solids processing capacity and adds process equipment units as needed. |
N/A |
| 5 |
Hastings Plant - Consists of siting, facility planning, design and construction of a new 5 mgd wastewater treatment plant to serve the community of Hastings. The new plant will include phosphorus and ammonia removal. The new plant will replace the existing plant located in downtown Hastings near the Mississippi River. |
Prelim. Engr. and Land Purchase |
| 6 |
St Croix Headworks and Disinfection - Consists of modifications to the plant's headworks, along with the replacement of screening and grit removal equipment. The project also provides for the replacement of the existing ultraviolet (UV) disinfection system. The project is planned to be initiated in 2013. |
N/A |
| Map ID | Project Name and Description | Phase Authorized in 2011 |
|---|---|---|
| (Click on the project name for additional project details) | ||
| 7 |
Blue Lake Plant Improvements - Consists of replacing the existing gaseous chemical effluent disinfection system with liquid chemical disinfection; modifying the existing secondary treatment facilities to remove phosphorus to meet the 1 mg/l annual average limit; rehabilitation of facilities nearing the end of their useful life; improvements to the solids processing facilities and odor control; the addition of anaerobic sludge digestion to supplement the existing sludge dryer for reliability and to recover energy for dryer use; and improvements to plant utility systems. The project also includes the staged expansion of the plant's capacity. |
Construction |
| 8 |
Seneca Disinfection & Phosphorus - Consists of replacing the existing gaseous chemical effluent disinfection system with liquid chemical disinfection, modifying the existing secondary treatment facilities to remove phosphorus to meet the 1 mg/l annual average limit; and improving/rehabilitating the mechanical and electrical systems. |
Construction |
| 9 |
Seneca Plant Solids Processing Improvements - Consists of improvements to the plant's solids processing system when the current facilities near the end of their useful life. The project is planned to be initiated in 2018. |
N/A |
| Map ID | Project Name and Description | Phase Authorized in 2011 |
|---|---|---|
| (Click on the project name for additional project details) | ||
| 10 | Bloomington-Edina-Richfield Area Improvements - This project will plan, design, and construct interceptor facilities to meet the conveyance capacity needs of the Bloomington, Edina, and Richfield area as redevelopment occurs along the I-494 corridor. Two major projects are included: (1) Relief gravity interceptor in Richfield; and (2) Lift station and forcemain in Bloomington. |
Construction |
| 11 |
Blue Lake System Improvements - This project will provide improvements to meet the long-term conveyance capacity, reliability, and rehabilitation/replacement needs of the Blue Lake Interceptor System. This system includes gravity sewers, 29 lift stations, and single forcemains from each lift station. Where cost effective, such as in the Victoria area, some lift stations will be replaced by deep gravity sewers using tunnel construction methods. In some cases, small lift stations will be consolidated. The remaining lift stations will be expanded and/or rehabilitated/replaced as necessary. Single forcemains will be upgraded to dual forcemains. Gravity sewers will be rehabilitated and expanded as necessary. The four major project areas are Victoria, Excelsior, Mound, and Wayzata. |
Construction |
| 12 |
Burnsville Interceptor Rehabilitation - Provides for the rehabilitation of approximately 17,500 feet of Interceptor 3-BV-35. Rehabilitation is required due to hydrogen sulfide corrosion, exposed reinforcement, inflow/infiltration, offset joints, separated joints, extensive root damage and cracks. |
Construction |
| 13 |
Chaska Lift Station - Provides for the design and construction of a new, larger pumping station at the former WWTP site, to provide long-term capacity to serve Chaska and Carver. The project includes the demolition of wastewater treatment facilities from the phased-out Chaska WWTP. |
Construction |
| 14 |
Chaska West Interceptor - Construction of a lift station, forcemain, and gravity interceptor sewer to convey flow from a service area that includes the cities of Chaska and Carver. |
Construction |
| 16 | Chaska-Shakopee Interceptor Improvements - Provides for the rehabilitation of the corrosion damaged gravity sewer portion of the this interceptor. The corrosion is extensive and has resulted in significant damage to the interior concrete surfaces of the pipe and maintenance structures. |
Construction |
| 16 |
East Maintenance Base - Consists of the planning, siting, design and construction of a new maintenance base for the interceptor maintenance staff in the east metro area. |
Preliminary Engineering and Design |
| 17 |
Elm Creek Interceptor - Consists of constructing a gravity interceptor system to provide long term interceptor service to the communities of Brooklyn Park, Corcoran, Dayton, Hassan, Maple Grove, Medina, and Plymouth. |
Construction |
| 18 |
Golden Valley Area Improvements - Consists of interceptor capacity relief for the Golden Valley-St. Louis Park area. |
Prelim. Engr. and Design |
| 19 | Hilltop Interceptor Rehabilitation - An inspection in December, 2006 revealed that the Hilltop 1-HT-100 Interceptor was in need of major rehabilitation or replacement. Phase I of the project was completed with a cooperative agreement with the City of Columbia Heights in 2008 and consisted of lining work for the Hilltop Interceptor 4-HT-100. Initiated in 2010, Phase II of the improvements includes replacement of 1,965 feet of 8” VCP sanitary sewer located on Monroe Street and trimming of protruding taps on 4th Street. |
Construction |
| 20 |
Hopkins System Improvements - Consists of rehabilitation/replacement of the existing 30-year old forcemain and lift station to provide long term, reliable service to the City of Hopkins and St. Louis Park. |
Construction |
| 21 | Interceptor 1-MN-310/320 Rehabilitation - These two sewers were originally constructed in Minneapolis in 1887 - 1888. Portions of these sewers are original brick construction. Pipe sizes vary from 3 feet to 10 feet diameter. The pipe length is 12 miles. These sewers will be evaluated to determine their rehabilitation needs. A deep tunnel connection to the Minneapolis East Interceptor will be considered as a means to ensure capacity and reliability of the system and to facilitate rehabilitation of the old sewers. |
Prelim. Engr. |
| 22 | Interceptor 1-MN-320 Reconnection and Improvements - This project represents the final phase of the original Minneapolis 1-MN-320 Improvements project. It involves reconnection of local Minneapolis sewers, the construction of a new access shaft, and crown repairs to a section of Interceptor 1-MN-320. The other two phases of the original project are complete and in operation. |
Construction |
| 23 |
Interceptor Rehabilitation Program - Provides funding to rehabilitate interceptor facilities which must proceed immediately based on the results of inspections. |
Construction |
| 24 |
Interceptor Rehabilitation Program - Major - This is a placeholder for rehabilitation of several major interceptors in the fully developed areas of the region. |
N/A |
| 25 | Interceptor Rehabilitation - Trenchless - Recent inspections and investigations noted infiltration and inflow (I&I) and deteriorating conditions on numerous interceptors. These conditions include Hydrogen Sulfide Corrosion, Infiltration and Inflow (I&I), Roots and Debris, Cracked Pipe, and Offset Joints. This project will use trenchless rehabilitation methods to correct the problems and restore the integrity and reliability of several interceptors in Chanhassen, Golden Valley, Lakeville, Maplewood, New Brighton, Newport, South St. Paul, and St Paul Park. |
Construction |
| 26 |
Interceptor WO-500 Rehabilitation - Video inspection of interceptor 1-WO-500 in Woodbury indicates significant hydrogen sulfide corrosion of the reinforced concrete pipe (RCP). This project will repair approximately 11,441 lineal feet of interceptor with Cured-in-place-Pipe (CIPP). |
Construction |
| 27 |
Lift Station Rehabilitation - Consists of improvements to Lift Stations L-3, L-6, L-7, L-10, L-13, L-30, L-35, L-56 and L-66. The project will replace obsolete, aging equipment and increase the lift stations' pumping capacity. The L-7 forcemain will also be replaced under this project. |
Construction |
| 28 |
Maplewood Interceptor Rehabilitation - This project provides for rehabilitation of the Interceptor 1-MW-413 in Maplewood. The project will fix offset joints, leaks and bad gaskets and eliminate sags where sedimentation builds up. |
Construction |
| 29 |
Meter Improvements - Consists of improvements including meter rehabilitation or replacement, temporary meter installation, and new meter installation. The project will upgrade MCES’ ability to measure flows for billing, operational, and planning purposes; and standardize meter equipment at similar facilities. |
Construction |
| 30 |
Mpls. Interceptor 1-MN-303 - Consists of the rehabilitation of Mpls Interceptor 1-MN-303 including: patching the bands; placing a concrete invert for the storm sewer (upper partition); and installing cured-in-place-pipe (CIPP) in the sanitary sewer interceptor (lower partition). The sag between MH17 and 16 will be repaired by replacing approximately 225 ft. of 36-inch RCP. |
Construction |
| 31 |
Mpls/St Paul Interceptor Improvements - Consists of improvements to the large metropolitan interceptors in the core area to rehabilitate aging facilities. The initial project includes rehabilitation of St Paul Interceptors 1-SP-214 and 1-SP-255. Another major project is relocation of the Oak Street Interceptor to accommodate the new Gophers Stadium for the University of Minnesota. The project will also result in separating the existing sanitary sewer from being located inside the storm sewer. |
Construction |
| 32 |
Northeast Interceptor Improvements - The 6901 diversion project will provide additional capacity to the northeast metropolitan service area (Forest Lake, Hugo, Centerville, and White Bear Lake Township) by relieving the capacity restriction caused by 3.4-mile reach of 36-inch RCP segment of the MSB 6901 Interceptor. Northeast Interceptor Phase I in St. Paul and Maplewood, will provide capacity to meet the long-term service needs of the Northeast area. |
Construction |
| 33 |
Northwest Interceptor Improvements - Consists of improvements to the interceptor system to serve planned growth in the northwest portion of the metropolitan area. The project consists of an integrated conveyance system from Highway 169 and 101st Avenue in Brooklyn Park on the west to the Coon Rapids Interceptor (CRI) on the east. The conveyance system will provide capacity relief for the Champlin-Anoka-Brooklyn Park (CAB) and the Elm Creek Interceptor (ECI), in-line storage for relief, and conveyance of flow across the Mississippi River to the CRI. The planned conveyance system will parallel the existing Elm Creek and CAB interceptors, continue east across the Mississippi River to a lift station on the east side of the river, and then end at the CRI. A new gravity interceptor will bring flow from Coon Rapids Lift Station 34 to the proposed lift station. Lift station 34 will be abandoned. |
Preliminary Engineering and Design |
| 34 |
Plymouth Forcemain Improvements - Consists of rehabilitation of the portions of the Plymouth Forcemain that act as a gravity sewer, which have experienced significant hydrogen sulfide corrosion damage. |
Construction |
| 35 |
Septage Management - During 2004, MCES completed a study to evaluate the effectiveness of this system and the impact that hauled liquid wastes has on the treatment system to determine the most efficient and cost effective method for treatment and disposal. The recommended plan provided for increased disposal site security, methods to record and monitor loads received, and minimization of adverse infrastructure impacts related to hauled liquid wastes (corrosion, sediment buildup and odors). Several changes to the Hauled Liquid Waste Management Program have been implemented to improve the control of discharges to the MDS, protect the infrastructure, improve security, and capture appropriate revenue costs. Under this project, the current septage site in Chanhassen is being upgraded to meet program requirements. Facilities are currently being designed for the Blue Lake Plant utilizing the prototype facility constructed at the Empire disposal site. In 2009, the septage facility the MCES purchased in Fridley replaced four septage sites in the north metro area. |
Construction |
| 36 | Southeast Anoka County Improvements - This project will plan, design, and construct a relief interceptor to provide additional capacity to serve Blaine, Circle Pines, Lexington, and Lino Lakes. |
Preliminary Engineering and Design |
| 37 |
South St. Paul LS/FM Improvements - Consists of the replacement of the screen handling facilities; electrical equipment; pumps and motors; odor control, standby power, wet well access and to the secondary building. The lift station portion of the project was completed in 2006. The project also includes the replacement of the existing forcemain with a dual forcemain for reliability of conveyance to the Metropolitan WWTP. This forcemain portion of the project includes river crossing and conveyance to the Metropolitan WWTP. |
Construction |
| 38 | St Bonifacius Interceptor Rehabilitation - The project consists of realigning the interceptor under Highway 7 and along County Road 92 and repairing a total of 3,505 lineal feet of interceptor with Cured-in-place-Pipe (CIPP) to remove I/I from the MCES interceptor system. |
Construction |
| 39 |
SWC Interceptor Lake Elmo Connections - This is the remaining phases of the original South Washington County Interceptor project. The project provides additional regional wastewater conveyance capacity for Lake Elmo at two locations on the Lake Elmo /Woodbury border. It consists of the Lake Elmo East Connection to convey wastewater from eastern Lake Elmo to the Eagles Point Plant and the West Connection to the WONE Interceptor to the Metro Plant. |
Construction |
| Map ID | Project Name and Description | Phase Authorized in 2011 |
|---|---|---|
| (Click on the project name for additional project details) | ||
| 40 |
Rural Area Improvements- Provides funding for acquisition and improvements to rural growth center wastewater treatment facilities that may be acquired and operated by the Metropolitan Council. Also provides funding for the acquisition of sites for future wastewater treatment plants to serve northwestern Hennepin County, south-central Carver County, and western Scott County. The project also provides funding for the acquisition of easements for future pipelines. |
WWTP Acquisition and Design |
| 41 | Crow River Water Reclamation Plant - Consists of siting, preliminary engineering, design and construction of a new water reclamation plant to serve the Crow River watershed communities in western Hennepin County. |
Prelim Engr. and Site Acquisition |
| 42 |
East Bethel WWTP - The project provides for sewered development of a newly designated Rural Growth Center served by a Metropolitan Council owned and operated wastewater treatment facility. This facility will include a water reclamation plant, non-potable water pipeline system, groundwater recharge (land application) system, and spray irrigation system. An interceptor sewers is included to serve Oak Grove in the future. |
Construction |
| 43 |
Elko-New Market Interceptor - Consists of the construction of an interceptor to phase out the existing Elko-New Market Plant. Wastewater from Elko-New Market will be conveyed to the Metropolitan Council's Empire WWTP. Construction of the interceptor is scheduled for completion in 2011. |
Construction |
| 44 | New Germany WWTP - The project provides for the construction of a new treatment plant in the community of New Germany. The Council has agreed to acquire the existing New Germany plant in 2015, and then to construct a new plant to provide capacity for growth. |
Construction |
| Map ID | Project Name and Description | Phase Authorized in 2011 |
|---|---|---|
| (Click on the project name for additional project details) | ||
| 45 |
Energy Conservation and Recovery - Provides for energy conservation and recovery improvements for the interceptor and treatment plant facilities, such as lighting, heating/ventilation and compressed air systems. |
Construction |
| 46 | Systemwide Odor Control Improvements - Provides for capital improvements to address odor problems in the MCES' conveyance and treatment system. Improvements include the collection and treatment of sewer gases with biofilters, chemical scrubbers, and/or carbon odor scrubbers; the installation of chemical feed facilities to control odors in critical areas of the system; and improvements to the airflow dynamics in large interceptors. |
Construction |
| 47 |
Small Systemwide Improvement Program - Provides for small systemwide improvement projects to interceptor or treatment plant facilities. Each project is generally less than $1,000,000. |
Construction |